PROJECT

JAWA SATU GAS INFRASTRUCTURE AND MARINE WORKS

Client :

Consortium Pertamina (Persero)-Marubeni Corporation and Sojitz

Project Description :

PT Pertamina (Persero) have formed a Consortium with Marubeni Corporation and Sojitz (“Owner”) for the development of LNG Floating Storage and Regasification Facilities including mooring system and gas transmission line i.e. offshore & onshore gas pipeline and Onshore Receiving Facility (ORF) facilities at the receiving point at Cilamaya site in North Java “Facilities”.

Project Location :

Cimalaya Wetan, Cimalaya, Karawang

Scope of work :

Fabricate, assembly, precommissioning, blasting/ painting and loadoout of Offloading Platform and Mooring Jetty including piles. Total Project weight is 5,047 ton, consist of:

Gas Offloading Platform (GOP)
Topside weight : 176 ton
Jacket weight: 146 ton
Pile weight : 101 ton

Mooring and Berthing:-

Mooring Dolphins

  • 4 Modules Mooring Dolphins total 528 ton
  • Mooring Dolphin Pile total: 1,152 ton

Berthing Dolphins

  • 4 Modules Berthing Dolphins total : 1,060 ton
  • Berthing Dolphin Pile total: 1,884 ton

CONTRACT PERIOD :

February 2020 – November 2020