Client :
Consortium Pertamina (Persero)-Marubeni Corporation and Sojitz
Project Description :
PT Pertamina (Persero) have formed a Consortium with Marubeni Corporation and Sojitz (“Owner”) for the development of LNG Floating Storage and Regasification Facilities including mooring system and gas transmission line i.e. offshore & onshore gas pipeline and Onshore Receiving Facility (ORF) facilities at the receiving point at Cilamaya site in North Java “Facilities”.
Project Location :
Cimalaya Wetan, Cimalaya, Karawang
Scope of work :
Fabricate, assembly, precommissioning, blasting/ painting and loadoout of Offloading Platform and Mooring Jetty including piles. Total Project weight is 5,047 ton, consist of:
Gas Offloading Platform (GOP)
Topside weight : 176 ton
Jacket weight: 146 ton
Pile weight : 101 ton
Mooring and Berthing:-
Mooring Dolphins
- 4 Modules Mooring Dolphins total 528 ton
- Mooring Dolphin Pile total: 1,152 ton
Berthing Dolphins
- 4 Modules Berthing Dolphins total : 1,060 ton
- Berthing Dolphin Pile total: 1,884 ton
CONTRACT PERIOD :
February 2020 – November 2020