Client :
CSTS (CHIYODA, SAIPEM, TRIPATRA AND SAE) JOINT OPERATION
Project Description :
BP Berau Tangguh LNG Train 3 is an LNG plant converting natural gas into liquid natural gas and send to Indonesia and overseas. Pipe installation and support pipe racks is one key suppoting for the project. Construction pipe racks modularization divided into total 75 modules, 26 modules are for middle route area and 49 modules for jetty area.
Project Location :
Bintuni, West Papua
Scope of work :
Assembly of pre-fabricate structural, fabrication and erection of pipe (CS, SS & Duplex) complete with support, load out of completed Modules.
- Piping fabrication and installation: 30,548 Dia-inch
- Steel Structure assembly : 1,824 MT
- Pipe support Fab & Erect : 90 tons
- Painting: 54.500 M2
- Cable Tray: 2,800 Meter
Project was started on October 2018 with first received of materials on January 2019 and finished February 2020. Last Modules load out was on End Apr 2020.
CONTRACT PERIOD :
October 2018 - April 2020